MWRA Project Update Including Scheduled Oak Street Area Detours

-A A +A

Work in Stoneham:

Under Contract 7478, MWRA contractors will install 7,800 linear feet of 48-inch diameter water main (Section 110) in Stoneham.

This work is expected to commence Spring 2016 and be complete in September, 2018.

 

Please click here to be redirected to the MWRA project update page 

If you would like to sign up for alerts as information becomes available for this project please click here.

Click here for map of the scheduled Oak Street detours